Conventional structure:
1. Two sets of mold embryos, the respective molding structures are more common: the front mold is the same, the rear mold is different (the second mold embryo is rotated 180 degrees). Note: There are certain techniques for fixing the mold on the injection molding machine; first fix one set and then fix the other set, mainly adjust the moving mold part of the other set (the code mold must be received with screws, and the code is generally not available). High requirements on flange size.
2. Side nail: There is no partial guide post.
3. The precision of the mold embryo is high, and it is generally shipped from Guangdong (more use of Futeba mold embryo).
4. Molding requirements: (1) primary glue, (2) secondary glue, (3) pre-pressing, (4) avoiding air; shrinkage does not need to be considered (about 2MM after general product glue).
Note for two-color molds: